We regularly inspect and maintain schools as part of a comprehensive and ongoing program to keep school assets in optimal condition and to ensure the safety and wellbeing of our school community across more than 2200 NSW schools.
The school holidays are the ideal time for a lot of maintenance and project work to take place in schools without disrupting learning.
Planned work over the school holidays at some schools may involve working with hazardous materials such as asbestos or lead. This may include proactive inspection, sampling, remediation or removal of the material.
For more information on how we work with hazardous materials, please visit our Managing Materials web page.
Below are lists of schools that have work involving hazardous materials taking place during the upcoming school holiday period. Some schools receive more detailed communication about work taking place at their school. In these instances, communications are published on the SINSW school webpage (use the search bar on this website to find your school).
Check the list to find out if your school is included. Please note:
- ACM refers to “asbestos-containing materials”.
- Safety measures, including air monitoring and fencing, will be in place as advised by the independent hygienist.
- All external work is subject to weather conditions.
2025 Term 3 Spring School Holidays
Spring School Holidays - Works Notification - 2025
(PDF 152 KB)
School holiday work school list A-F
|
School |
What work we’re doing and where |
More detail about the work involving hazardous materials |
|---|---|---|
|
Replacement of flooring in Buildings 1, 3, 5 and 7. |
Removal of bonded asbestos from the vinyl tiles under the existing floor, as listed in the school's asbestos register. The asbestos is being removed from 16 classrooms across buildings 1, 3, 5 and 7. |
|
|
Refurbishment of the girls toilets in Building B and boys toilets in Building D. |
The partition walls contain bonded asbestos. Material is currently undisturbed and in good condition. |
|
|
Removal of vinyl tiles under carpet from 4 rooms on the first floor of Building E and from the ground floor study in the library building. Removal of incinerator from a store room in the Technological and Applied Studies building. |
Vinyl tiles are known to contain bonded asbestos. |
|
|
Staff kitchen refurbishments in Building 11. |
Removal of existing kitchen and installation of new kitchen in staff room 12. |
|
|
Replacement of carpet in the staffroom on the first floor of the Administration Building. |
Removing and replacing the vinyl floor tiles known to contain bonded asbestos. The tiles are underneath the carpet and the material is currently undisturbed and in good condition. |
|
|
Replacement of 5 vermiculite ceilings and removal of ductwork in library building. |
Ceiling void in library building contains lead dust. Old ductwork contains asbestos. |
|
|
Replacing and replacing broken eave sheet in Building AM. |
Eave sheet known to contain bonded asbestos. |
|
|
Asbestos fragments in school's main entrance car park. |
Bonded asbestos was identified and removed from the car park during school holidays. The area was immediately barricaded after the discovery and relevant staff informed. |
|
|
Replacement of carpet and vinyl tiles in one of the art classrooms in Building G |
Removal of vinyl tiles that are known to contain bonded asbestos, the material is currently undisturbed and in good condition. |
|
|
Remediation mould works in Building 5 & 6. |
Removal of mould in Building 5 in classroom 1 and Building 6 in classrooms 18 and 28. |
|
|
Upgrade works to provide accessible bathroom and feeding room in Building G |
Removal of ceiling lining known to contain bonded asbestos, the material is currently undisturbed and in good condition. |
|
|
Cleaning and removal of paint from windows located on the first floor of Building A2. |
The putty in the window frames contains bonded asbestos. The putty will be sealed with silicone and encapsulated with aluminium angles following cleaning. Material is currently undisturbed and in good condition. |
|
|
Removing bathroom partitions in Building B PDHPE toilets. |
The partition walls contain bonded asbestos. Although no students were onsite, fencing and air monitoring was in place at the school as safety measures. All works were completed in the school holidays. |
|
|
Replacement of external stairs and repair of concrete footpaths near Building A, the demountable building, and Building L. |
Replacement of external stairs in Building A as well as concrete footpath repairs in the home economics area of demountable building 17741 and Building L. |
|
|
Replacement of flooring in the administration building. |
Removal of bonded asbestos from the vinyl tiles under the existing flooring in the movement areas in the administration building. Material is currently undisturbed and in good condition. |
|
|
Laying of new turf and irrigation on the sports field. |
Non hazmat. |
|
|
Replacement of cracked window in the school hall in Building H . |
Window putty is known to contain bonded asbestos, the material is currently undisturbed and in good condition. |
|
|
Installation of switchboards to the library building and associated electrical works. |
Removal of ACM in the electrical board. |
|
|
Removing and replacing broken eave sheet in Building H. |
Eave sheet known to contain bonded asbestos. |
|
|
Replacement of carpet in classrooms on the ground floor and first floor of Building C. |
Removing and replacing the vinyl floor tiles known to contain bonded asbestos. The tiles are underneath the carpet and the material is currently undisturbed and in good condition. |
School holiday work school list G-L
|
School |
What work we’re doing and where |
More detail about the work involving hazardous materials |
|---|---|---|
|
Replacing carpet and removing vinyl flooring underneath carpet in several classrooms and offices in the Administration Building (D Block). |
Removal of vinyl flooring which contains bonded asbestos. Material currently undisturbed under existing carpet and in good condition. |
|
|
Replacement of floor covering in administration Building C. |
Replacing vinyl floor tiles in staff rooms 7 and 9 and storerooms 8, 14, 15 and 16 in Building C that are area known to contain bonded asbestos. The material is currently undisturbed and in good condition. |
|
|
In ground remediation in a small area near the northern boundary and the elevated basketball court. |
Bonded asbestos fragments removed from the ground in an area already listed on the school’s asbestos management plan. Fragments were removed and tested, the ground cleared and the area was reopened. |
|
|
Removal of ACM contained within the drain spouts of covered walkway no. 8 in the main quadrangle. |
Removal of ACM contained within the drain spouts of the covered walkway. |
|
|
Removing vinyl tiles and replacing the flooring in one classroom each in buildings A and B. |
Removal of vinyl tile flooring containing bonded asbestos. |
|
|
Replacing carpet and removing vinyl flooring underneath carpet in several classrooms and storerooms within Block 6. |
Removal of vinyl flooring which contains bonded asbestos. Material currently undisturbed under existing carpet and in good condition. |
|
|
Removal of bonded asbestos from the vinyl tiles in storeroom 14, Building B. |
Vinyl tiles are known to contain bonded asbestos, the material is currently undisturbed and in good condition. |
|
|
Replacement of damaged external wall sheets in Building C. |
Non hazmat work. |
|
|
Replacement of flooring in the movement areas of Building B. |
Removal of bonded asbestos from the vinyl tiles under the existing flooring in the movement areas in Building B. Material is currently undisturbed and in good condition. |
School holiday work school list M-S
|
School |
What work we’re doing and where |
More detail about the work involving hazardous materials |
|---|---|---|
|
Removal and replacement of wall linings in the staff room demountable. |
Removal of wall lining known to contain bonded asbestos in the staff room demountable. Material is currently undisturbed and in good condition. |
|
|
Cleaning of print room in Building A. |
Deep clean of the printing room in Building A due to mould smell. All resources that were cleaned and moved out of the room have now been returned. |
|
|
Removal of vinyl tiles in Building F. |
Removal of vinyl tiles that are known to contain bonded asbestos, the material is currently undisturbed and in good condition. |
|
|
Replacement of vinyl flooring in Building I. |
Replacing vinyl floor tiles glued under the carpeted area known to contain bonded asbestos. The material is currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in Building A. |
Removing of tiles known to contain bonded asbestos. The material is currently undisturbed and in good condition. |
|
|
Removal of asbestos fragments next to school driveway and agricultural plot. |
Four pieces of suspected bonded asbestos were found on school grounds during the holidays. A hygienist was engaged to attend, test pieces and remove them before students returned in Term 4. |
|
|
Replacement of floor coverings in Building C. |
Removing and replacing floor tiles known to contain bonded asbestos. The tiles will be replaced in classroom 4. Material is currently undisturbed and in good condition. |
|
|
Replacement of vinly flooring in Building A. |
Replacing floor coverings, underneath carpet is known to contain bonded asbestos. The vinyl tiles are currently glued to floor boards. |
|
|
Toilet refurbishment in Building C. |
Removal of bonded asbestos in toilet partitions and ceiling linings, as listed in the school's asbestos register. Material is currently undisturbed and in good condition. |
|
|
Replacement of damaged soffit sheets in the entrance area at the western end of the science and music area in classroom 16 in Building F. |
Soffit sheets are known to contain bonded asbestos, the material is currently undisturbed and in good condition. |
|
|
Removing vinyl tiles and replacing the flooring in the preschool (Building I). |
Removal of vinyl tile flooring containing bonded asbestos. Material currently undisturbed and in good condition. |
|
|
Replacement of a cracked window in a ground floor classroom in Building F. |
The grey putty in the window frame contains bonded asbestos. Putty will be removed when installing the new window. Material currently undisturbed and cracked glass is secured. |
|
|
Removal of bonded asbestos will take place in classrooms 1 and 3 of Building B. Replacement of carpet and painting will be carried out in classroom 1, and painting will be done in classroom 3. |
Removal of bonded asbestos will take place in classroom 1, the material is currently undisturbed and in good condition. |
|
|
Removal of bonded asbestos in wall lining and replacing plaster, painting and carpet in classrooms 2 and 3 in Building A. |
Wall lining is known to contain bonded asbestos, the material is currently undisturbed and in good condition. |
|
|
Cleaning of sports storeroom located in Building J |
Environmental cleaning, air scrubbing and painting to remove mould located in the Building J sports storeroom. |
|
|
Replacement of floor coverings in Building B . |
Removing and replacing floor tiles known to contain bonded asbestos. The tiles will be replaced in classrooms 3, 6, 18, 20, 21, 28. |
|
|
Replacement of flooring in Building A and Building B. |
Removing and replacing the vinyl floor tiles known to contain bonded asbestos. The tiles are underneath the carpet and the material is currently undisturbed and in good condition. |
|
|
Floor coverings in the 2 rooms next to library being repaired. |
While replacing mould-affected ceiling, walls, cupboards and floor coverings in the 2 rooms next to the library, bonded ACM was discovered and was remediated in one day during school holidays. |
|
|
External wall of sports shed Building H to be repaired. |
A ball was kicked into the wall displacing asbestos wall lining. Wall repaired during school holidays. |
|
|
Upgrading of sports court with new surface, basketball hoops and backboards. |
Non hazmat. |
School holiday work school list T-Z
|
School |
What work we’re doing and where |
More detail about the work involving hazardous materials |
|---|---|---|
|
Removal of bonded asbestos in ceiling sheets, along with upgrades to ceiling repairs in classroom 5, as well as CCTV installation in Building F. |
Ceiling sheets are known to contain bonded asbestos, the material is currently in good condition. |
|
|
Replacement of flooring in Buildings B and E. |
Removal of bonded asbestos in the vinyl tiles under the existing floor, in multiple classrooms of buildings B and E as listed in the school's asbestos register. |
|
|
Replacement of floor coverings in Demountable Building D. |
Replacing vinyl floor tiles glued to floor boards, known to contain bonded asbestos. The material is currently undisturbed and in good condition. |
|
|
Removal and replacement of the damaged exterior weatherboard on northern wall of Building H, staff resources room, next to Library block. |
Existing weatherboards have lead paint in Building H. |
|
|
Replacing a window in the library. |
The putty in the window frame is suspected to contain asbestos. This will be removed when installing the new windows. |
|
|
Mould found in 2 Building E science labs. |
Although mould was identified, air quality remained normal and full remediation was carried out in the school holidays. All appropriate measures were taken in line with the hygienist's recommendations. |
|
|
Removal of bonded asbestos in vinyl tile flooring in storerooms 1 and 2 in Building B, along with upgrades to accessibility and toileting facilities. |
Vinyl tiles are known to contain bonded asbestos, the material is currently undisturbed and in good condition. |
|
|
Installation of new carpets in buildings B and I. |
Removal of vinyl tiles that are known to contain bonded asbestos, the material is currently undisturbed and in good condition. |
|
|
Removal of bonded asbestos from the vinyl tiles under the existing carpet and installing new carpet in the Principal's office in room 12 in Building A. |
Vinyl tiles are known to contain bonded asbestos, the material is currently undisturbed and in good condition. |