School holiday work
We regularly inspect and maintain schools as part of a comprehensive and ongoing program to keep school assets in optimal condition and to ensure the safety and wellbeing of our school community across more than 2200 NSW schools.
The school holidays are the ideal time for a lot of maintenance and project work to take place in schools without disrupting learning.
Planned work over the school holidays at some schools may involve working with hazardous materials such as asbestos or lead. This may include proactive inspection, sampling, remediation or removal of the material.
For more information on how we work with hazardous materials, please visit our Managing Materials web page.
Below are lists of schools that have work involving hazardous materials taking place during the upcoming school holiday period. Some schools receive more detailed communication about work taking place at their school. In these instances, communications are published on the SINSW school webpage (use the search bar on this website to find your school).
Check the list to find out if your school is included. Please note:
- ACM refers to “asbestos-containing materials”.
- Safety measures, including air monitoring and fencing, will be in place as advised by the independent hygienist.
- All external work is subject to weather conditions.
2025-26 Term 4 Summer School Holidays
Summer School Holidays - Works Notification - 2025-26
(PDF 150 KB)
School holiday work school list A-F
|
School |
What work we’re doing and where |
More detail about the work involving hazardous materials |
|---|---|---|
|
Refurbishment of the boys and girls amenities in Building C. |
Removal of the partitions containing bonded asbestos in both the girls and boys bathrooms in Building C as listed on the School Asbestos Management Plan. Materials are currently undisturbed and in good condition. |
|
|
Painting the internal movement and stairwell areas in Building C |
No hazardous material involved. |
|
|
Replacement of floor coverings in classroom 9 demountable, north of the sports court. |
Removal of existing vinyl flooring which contains bonded ACM. Flooring not previously listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in Helen's room in Building H. |
Removal of existing vinyl flooring which contains bonded ACM as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in the offices and movement area adjacent to the principal’s office in the Administration block in Building A. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in the movement area of Building C. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor replacement in rooms in the Administration block in Building F. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in Building H |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Removal of decommissioned hot water boiler and pipes for the hydrotherapy pool in the plant room in Building B. |
Removal of hot water boiler and pipes in the plant room, known to contain bonded asbestos as listed on the School Asbestos Management Plan. Materials are currently undisturbed and in good condition. |
|
|
Floor covering replacement in Building A |
Removal of vinyl tiles assumed to contain bonded asbestos, recently identified but not listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Removal of vinyl flooring in 2 movement areas of Building A. |
The vinyl flooring contained bonded asbestos as listed in the School Asbestos Management Plan. |
|
|
Refurbishments to the support class areas in Building E. |
No hazardous material involved. |
|
|
Floor covering replacement in Building B |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Accessibility upgrades across the school including ramps and covered walkways as well as refurbishments to Building 1. |
Removal of lead-painted weather boards and removal of internal wall linings known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Removal of air conditioning units and ducting across all music classrooms in Building A and all TAS classrooms in Building B. |
No hazardous materials involved. |
|
|
Internal painting of the all the rooms in the Administration block in Building A, all rooms in Building B, all rooms in the support unit in Building C, all rooms in Building D, all rooms in the library building in Building E and all rooms in the canteen building in Building F. |
No hazardous materials involved. |
|
|
Floor replacement in all classrooms and storerooms in Building B, Kindergarten classroom and storerooms in Building C and the learning centre and occupational therapy room in Building E. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the movement areas and classrooms in Building B. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Environmental clean of 2 classrooms in Building D following a recent storm. |
No hazardous material involved. |
|
|
Replacement of floor coverings in all rooms in Building D. |
Removal of existing vinyl flooring which contains bonded ACM as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Removal of cement blackboard from a classroom in Building G. |
Removal of cement blackboard which contained bonded asbestos. Material recently identified but not listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of gable ends in Building E. |
Removal of fibro sheeting which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Removal and replacement of the eave sheeting on the external awnings to buildings A, C and F and to the eave sheeting on the covered walkways between buildings A and C and adjoining Building F. |
Removal of known asbestos in the external awnings as listed on the School Asbestos Management Plan. Removal of asbestos in the eave sheeting of the covered walkways identified during scheduled demolition work. |
|
|
Replacement of floor coverings in 6 classrooms, both computer rooms, the computer storeroom and 3 staff offices in Building A. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in one of the metal work classrooms and 2 music classrooms in Building B. |
Removal of existing vinyl flooring which contains bonded ACM. Flooring not previously listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor covering in the kitchen in Building B. |
Removal of existing vinyl flooring which contains bonded ACM. Flooring not previously listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Toilet refurbishment in Building A |
No hazardous material |
|
|
Floor covering replacement in buildings A and B. |
Removal of existing vinyl tiles which contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in Building A |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Upgrades to the girls toilets within Building E. |
Removal of ceiling sheeting known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Minor refurbishments to windows of a classroom in Building C1. Repair of eave sheets in the corridor outside of Building C1 and in the corridor on the first floor of Building C2. |
Removal of eave sheets and window putty known to contain bonded asbestos as listed on the School Asbestos Management Plan. |
|
|
Repairs to the shade structure and concrete surfaces behind Building B. |
No hazardous material involved. |
|
|
Refurbishments and safety improvements to buildings H, J, K and L. |
Removal of lead-painted weather boards. |
|
|
Replacement of termite-damaged timber flooring in the movement area on the first floor of the Administration Building. |
Any ACM fragments in the subfloor void of that area will be removed if discovered during the flooring replacement. |
|
|
Removal of vinyl tiles underneath the existing carpet of the eastern classroom in Building A. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Construction of a new Yoga studio. Work will also include the removal of a pergola in order to begin work on the new yoga studio, which will be located where the pergola currently sits. |
No hazardous material involved. |
|
|
Removal and replacement of an external awning on a demountable classroom on the south-eastern side of the school. |
Removal of known bonded asbestos in the external awning as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Floor covering replacement in buildings A and E |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Floor covering replacement in Building E |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Floor replacement in all rooms in the Administration block in Building F. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Remediation and replacement of part of the roof to the art classroom demountable, north of Building B. |
Remediation of the roof due to a fallen branch. Removal of known bonded asbestos in the ceiling linings as listed on the School Asbestos Management Plan. |
|
|
Replacement of walls in the staff kitchen in Building C. Removal of sanitary unit and associated pipes in Building G. |
Removal of the wall sheets in the staff kitchen in Building C and removal of sanitary unit and associated pipes in Building G which contain bonded asbestos as listed on the School Asbestos Management Plan. Materials are undisturbed and in good condition. |
|
|
Removal of floor coverings in the storeroom and work room of the Administration block in Building A. Refurbishing the boys' and girls' toilets in the Hall in Building C and toilet block in Building E. |
Removal of existing vinyl flooring containing bonded asbestos in Building A, and removal of the partitions containing bonded asbestos in the toilets in buildings C and E. All material listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Refurbishments to the window areas in buildings A, B, C, D, E, F, G and H. |
Removal of the window putty known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition |
|
|
Installation of a new water tank. |
No hazardous material involved. |
|
|
Removal and upgrade to the current play equipment. Removal of synthetic turf overlay and installation of softfall under play equipment. |
No hazardous materials involved. |
|
|
Removal and replacement of soffit linings to the canteen building in Building B. Removal and replacement of soffit linings to the external walkways around Building D, Building F, Building G and Building H. |
Removal of bonded asbestos soffit sheeting in the linings of the roof to Building B as listed on the School Asbestos Management Plan. Removal of bonded asbestos soffit sheeting in the linings of the covered walkways to buildings D,F, G and H. Materials are currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the learning space in Building C. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in all classrooms in Building A and Building D. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in 2 classrooms, the computer room and computer storeroom in Building F. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Toilet refurbishment in building A and C and sewer upgrade |
Removal of known bonded asbestos in toilet partitions as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Floor replacement in all classrooms in Building C. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in all rooms in the Administration block in Building A, all rooms in the canteen building in Building C, all rooms in Building E and all rooms in Building F. |
Removal of existing vinyl flooring which contains bonded ACM as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Converting classrooms in Building I into support units |
No hazardous material involved. |
|
|
Replacement of floor lining and sections of interior lining within the principal's office and staffroom. |
Removal of floor lining and sections of interior linings affected by mould. The mould-affected area was previously tested and a hygenist confirmed the space could be occupied until these repair works could take place. |
|
|
Electrical switchboard upgrades to the distribution boards in several locations across Building A, C, F and G. |
Removal of known asbestos located in the electrical distribution boards as listed on the School Asbestos Management Plan. Materials are currently undisturbed and in good condition. |
|
|
Repair of termite-damaged timber framing, walls and ceilings in the staff toilets and one movement area within the library building. |
Wall and ceiling linings containing bonded asbestos, as identified in the School Asbestos Management Plan, will be replaced with fibre cement sheeting. Material is currently undisturbed and in good condition. |
|
|
Resurfacing the school driveway and carpark. |
No hazardous material involved. |
|
|
Toilet refurbishment in Building D |
Removal of known bonded asbestos in toilet partitions as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of floor coverings in all the classrooms in Building B and Building C. |
Removal of existing vinyl flooring which contains bonded ACM. Flooring not previously listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Converting classrooms in Building A into support units |
Removal of known bonded asbestos from floor coverings as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Installation of new windows across all rooms in Building A. |
Removal and replacement of eave sheets known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Upgrades to the support kitchen in Building H. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Removal of debris from ground after erosion, north of Building HC between the demountables. |
Fragments of bonded asbestos were identified by the contractor during removal of debris from ground after erosion. The identified material has been removed. |
|
|
Replacement of floor coverings in 2 storerooms and the general learning space in the Administration block in Building A. |
Removal of existing vinyl flooring which contains bonded asbesos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Installation of a new roof to the school hall in Building B. |
Lead dust remediation from the roof cavity of Building B in preparation for the roof replacement. Lead dust is currently undisturbed. |
|
|
Floor covering replacement in all 3 classrooms on first floor of the Administration block in Building A. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacing exterior soffits with mini orb metal sheeting in Building D and Building A ceilings. |
Removal of exterior sheeting and soffits containing bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Toilet refurbishment in Building C. Wifi upgrade behind Building A. |
Removal of known bonded asbestos in toilet partitions and ceiling linings as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. No hazardous material involved in wifi upgrade. |
|
|
Floor covering replacement in Building B. |
Removal of existing vinyl tiles which contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Removal and replacement of soffit linings to the external walkways around buildings E, F and I. |
Removal of bonded asbestos soffit sheeting on the linings of the covered walkways as listed on the School Asbestos Management Plan. Materials are currently undisturbed and in good condition. |
|
|
Painting the internal walls and ceilings in Building A and refurbishing the canteen facilities in Building B |
No hazardous material involved. |
|
|
Canteen facilities refurbishment in Building D |
Removal of vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
School holiday work school list G-L
|
School |
What work we’re doing and where |
More detail about the work involving hazardous materials |
|---|---|---|
|
Refurbishments to the student toilets in Building F. |
Removal of ceiling linings containing bonded asbestos, as identified in the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Toilet refurbishment in buildings C and E |
Removal of existing toilet partitions and ceiling linings which contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in all rooms on the ground floor of the Administration block, the HSIE classrooms on the first floor in Building A and the classrooms and staff studies rooms in Buildings D and E. |
Removal of existing vinyl flooring which contains bonded ACM as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in all rooms in the Administration block in Building A, all classrooms in buildings B and C and the infants classrooms in buildings G and I. |
Removal of existing vinyl flooring which contains bonded ACM as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Refurbishment and replacement of veranda to Building A. |
Removal of bonded asbestos from the veranda as listed on the School Asbestos Management Plan Material is currently undisturbed and in good condition. |
|
|
Removal and upgrade to the current play equipment. |
No hazardous materials involved. |
|
|
Remediation of in-ground asbestos on the eastern back boundary. |
Removal of in-ground asbestos as identified in the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Improvements to various rooms across buildings A, B, C, F and I with installation of new carpet and vinyl flooring. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Improvements to the hallways in Building B. Shade sail to be installed in courtyard area central to Building B. |
Removal of cement sheeting containing bonded asbestos as identified in the School Asbestos Management Plan. Material is undisturbed and in good condition. No hazardous material involved in shade sail work. |
|
|
Replacement of floor coverings and wall linings to one of the storerooms in Building B and the classroom in Building M. |
Removal of existing vinyl flooring and wall linings which contains bonded ACM as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the movement area, storeroom and 2 office spaces in Building E. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in Building B |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of floor coverings in one of the classrooms and both storerooms in Building K. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in Building B |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of floor coverings in the storeroom in Building C, the science and art classrooms in Building G and the computer lab in Building H. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the staffroom in Building A, library in Building D and classrooms in Building H. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the Administration block in building B. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Repairs to the concrete surface of the playground. |
No hazardous material involved. |
|
|
Floor covering replacement in Building A classrooms and movement area |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of floor coverings in 2 classrooms in the TAS block in Building B. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the visual arts and the design and technology classroom in Building D and the Deputy Principal's office in Building F. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in 3 movement areas and 4 storerooms in the TAS block in Building 300, a storeroom and staff room in the computer learning block in Building 700 and a storeroom and movement area in the PDHPE block in Building 800. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Repairs and repainting of the external walls of Building C. |
Repainting of lead painted surfaces and removal of timber window frames. |
|
|
Accessibility upgrades in Building D including a new ramp and wheelchair accessible doorways. |
No hazardous material involved. |
|
|
Upgrades to classrooms in Building A including repainting the walls, doors, frames and skirting boards. |
Removal of wall linings known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Floor covering replacement in the bag room of stage 1 classroom and the staffroom in Building D. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Upgrades to the internal hallways on the ground and first floor of Building B. |
Removal of vinyl tiles under carpet and replacement of wall sheets containing bonded asbestos from the internal hallways on the ground and first floor of Building B as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Refurbishment of the boys, girls and staff toilets in Building A. Replacement of floor coverings in all the movement areas and classrooms in Building A. |
Removal of bonded asbestos in toilet partitions and ceiling linings, removal of existing vinyl flooring which contains bonded ACM as listed on the School Asbestos Management Plan. Material is currently undisturbed and in good condition. |
|
|
Repainting the interior of buildings A, B, C and D. |
No hazardous material involved. |
|
|
Removal of vinyl flooring in 2 classrooms on the ground floor of Building C. |
Removal of vinyl tiles and adhesive containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of floor coverings in 2 classrooms in Building B. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Refurbishing bathrooms in the Administration block in Building AM, staff amenities in Building C3, student amenities in Building EL and student amenities in Building HC. |
Removal of the toilet partitions containing bonded asbestos in all amenities in Building AM, Building C3, Building EL and Building HC as listed on the School Asbestos Management Plan. Materials are currently undisturbed and in good condition. |
|
|
Extension and refurbishment of Building E to create additional learning spaces and student facilities. |
Removal of existing ceiling linings assumed to contain bonded asbestos, recently identified but not listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Refurbishment of 3 classrooms and a practical activity area in heritage Building E to address termite damage, including framing repairs, painting and carpet replacement. |
Building E is listed on the School Asbestos Management Plan. The building will be isolated during works. Material is undisturbed and in good condition. |
|
|
Classroom refurbishment in Building H and resurfacing of quadrangle area. |
No hazardous material involved. |
|
|
Floor replacement in the library movement area in Building B. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in buildings A, F and G. Upgrade of LED lighting in Building G. |
Removal of existing vinyl tiles which contain bonded asbestos, as well as removal of existing known bonded asbestos between ceilings and fluorescent lights as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacing carpet in various classrooms and store rooms in buildings 1, 2, 4 and 6. Maintenance works to resurface part of the playground between Buildings 4 and 5, with the area safely enclosed by site fencing. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. No hazardous material involved in resurfacing work. |
|
|
Remediation of roof cavity ahead of Building B roof replacement |
Lead dust remediation from the roof cavity of Building B in preparation for roof replacement and restoration work. Lead dust is currently undisturbed. |
|
|
Installation of a new air conditioning unit across all rooms in Administration building in Building J and all rooms in the staff room in Building M. |
No hazardous materials involved. |
|
|
Removal and replacement of eaves and roof of buildings J, K and L. |
Removal of existing eaves and gables which contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of two cracked glass windows in classrooms in Building D and Building B. |
Removal of the window putty known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of floor coverings in the classrooms on level 1 in Building I. |
Removal of existing vinyl flooring which contains bonded ACM as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
School holiday work school list M-S
|
School |
What work we’re doing and where |
More detail about the work involving hazardous materials |
|---|---|---|
|
Repairs to the hall in Building W due to termite damage. |
No hazardous material involved. |
|
|
Installation of a new roof and upgrades to rooms in Building A including new windows on the first floor and minor internal refurbishments. Installation of new lights in the sports court COLA shelter. |
Removal of window frames and roof eaves known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Improvements to outside areas surrounding buildings A and D and grounds. Floor covering replacement in Building H. |
No hazardous material involved in outdoor works. Removal of existing vinyl tiles which contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in Building B. |
Removal of existing vinyl tiles which contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Refurbishment of staffroom in Building A, including replacement of cupboards and flooring. |
Wall and ceiling linings containing bonded asbestos, as identified in the School Asbestos Management Plan, will be replaced with gyprock. Material is currently undisturbed and in good condition. |
|
|
Floor maintenance of movement area in Building A, floor replacement in all rooms in Building B and painting of handrail in buildings A and B. |
Removal of existing vinyl flooring in building B which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Roof replacement and refurbishment of the hall in Building E |
Removal of known bonded asbestos from the roof eaves as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of floor coverings in the staff office in Building C, 2 classrooms and the practical activities area in Building E and all classrooms and the cleaning storeroom in Building F. |
Removal of existing vinyl flooring which contains bonded asbestos in the one of the classrooms and the cleaning storeroom in Building F, as listed on the School Asbestos Management Plan. Materials currently undisturbed and are in good condition. |
|
|
Refurbishment of the toilets in Building A. |
No hazardous material involved. |
|
|
Floor covering replacement in Building A |
No hazardous material involved. |
|
|
Removal of vinyl flooring in a classroom on the first floor of Building D. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Refurbishment of support unit class in Building 7. |
Removal of vinyl floor tiles and glue containing bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacing carpet in 2 classrooms in Building D and 2 classrooms in Building E. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Toilet refurbishment in Building H |
Removal of toilet cistern containing assumed bonded asbestos, recently identified but not listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Ceiling repairs in the demountable principal's office. |
Removal of existing ceiling linings assumed to contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed. |
|
|
Repainting the exterior of Building B. |
Remove lead paint and repaint external walls of Building B. |
|
|
Replacement of carpet and vinyl floor coverings and internal painting of the administration offices and stage 1 classroom in Building A, stage 3 classrooms in Building B and stage 2 classrooms in Building C. Removal of old, and construction of new playground edging around the Covered Outdoor Learning Area (COLA). |
No hazardous materials involved. |
|
|
Replacement of floor coverings in the library in Building C and the hall in Building D. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in all rooms in the Administration building in Building A and all classrooms in Building B. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in all administration rooms in Building A and the movement area and 3 classrooms in Building D. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor replacement in both homebase rooms, craft store room and movement area of the Administration building in Building A. |
Removal of existing vinyl flooring which contains bonded ACM as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the stage 1 demountable classroom at the southern end of the COLA. Refurbishment of staff and student amenities in Building D. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Removal of bonded asbestos from the roof eaves, soffits and toilet partitions in the toilets in Building D as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Accessibility upgrades across the school including safety line marking and other improvements. |
No hazardous material involved. |
|
|
Floor covering replacement in the Building B movement area |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of floor coverings in one of the staffrooms in Building C and the interview room in Building D. Window repairing in the gymnasium in Building K. |
Removing assumed asbestos-containing vinyl flooring as part of flooring replacement in Building C and Building D as listed on the School Asbestos Management Plan. Materials are currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the support unit classrooms in Building A. Refurbishment of the amenities in Building E. |
Removing assumed asbestos-containing vinyl flooring as part of flooring replacement. Removal of bonded asbestos in toilet ceiling linings as listed in the school's asbestos register. Material is currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the movement area in Building G. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacing covered walkways along the top oval. |
No hazardous material involved. |
|
|
Accessibility upgrades across the school including ramps and covered walkways. Replacing the carpet in 2 classrooms on the first floor of Building C1. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Floor replacement and internal painting of all rooms in the Administration block in Building A, bag storage in Building B, all rooms in Building E and all rooms in the library block in Building F. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Planned remediation of foundation under new rubber softfall on the eastern side of Building D. |
Encapsulation of soil, which contains bonded asbestos, as listed on the School Asbestos Management Plan by covering with a fabric lining and topping it with a clean soil. |
|
|
Replacement of floor coverings in storerooms, staff rooms, movement area, clerical office and computer rooms in the Administration block in Building A. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor replacement in the library and classroom in Building B. |
Removal of existing vinyl flooring which contains bonded ACM as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings and internal painting of the general storeroom, general learning space and resource storeroom in Administration/music block in Building A. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in all rooms in the Administration block in Building A. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Resurfacing of area between the car park and Building E. |
No hazardous material involved. |
|
|
Refurbishment of staff amenities and replacement of floor coverings in all rooms in the Administration block in Building A. |
Removal of existing flooring and toilet partitions which contains bonded asbestos as listed on the School Asbestos Management Plan. All materials are currently undisturbed and in good condition. |
|
|
Replacement of carpet and vinyl tiles in 2 Year 6 classrooms in Building G and 2 support unit classrooms in Building E. |
Removal of vinyl tiles that are known to contain bonded asbestos as listed on the School Asbestos Management Plan. The material is currently undisturbed and in good condition. |
|
|
Interior painting of level 1 in Building A. |
Encapsulation of lead paint in ceiling. Moderate flaking present, with area generally undisturbed and contained. |
|
|
Floor covering replacement in Building 12. |
Removal of existing vinyl tiles which contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in Building A. |
Removal of existing vinyl tiles which contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in Building D |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Roof replacement of Building C including the school hall, canteen and covered walkways 1 and 2. |
No hazardous material involved. |
|
|
Repainting of external walls to Building E, F and G. |
Removing lead-based paint from cladding on Buildings E, F and G. |
|
|
Upgrades and repairs to the ceilings of multiple rooms in Building F. |
Encapsulation of friable asbestos in the ceiling cavity of Building F, as identified in the School Asbestos Management Plan. Material is currently secure. |
|
|
Floor covering replacement in the Building F movement area |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Refurbishment of the toilet blocks in Building D. |
Removal of wall and ceiling sheets as well as cubicle partitions known to contain bonded asbestos, as identified in the School Asbestos Management Plan. Material is currently undisturbed and in good condition. |
|
|
Toilet refurbishment in Building C. |
Removal of known bonded asbestos in toilet partitions as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Construction of a classroom for the Clontarf boys program. |
No hazardous material involved. |
|
|
Removal of exterior paint from Building F. |
Removal of lead paint on external surfaces. |
|
|
Repair portion of flooring in the decking area of the canteen block. |
No hazardous material involved. |
|
|
Replacement of asphalt on the eastern side of buildings A, B, C and the carpark area. |
Fragments of bonded asbestos were identified in soil by the contractor during excavation of the existing asphalt. The identified material has been removed. |
|
|
Installation of flood lights and storage shed on the sport oval. |
No hazardous material involved. |
|
|
Upgrades to the shade sail and posts in the playground on the northern side of Building B. |
No hazardous material involved. |
|
|
Removal and replacement of soffit linings to the outdoor learning area in Building C. Floor replacement in the sick bay, print room and store room in the Administration block in Building A, the movement area in the stage 3 classrooms in Building D and movement area in the stage 2 classrooms in Building E. |
Removal of soffit sheeting containing bonded asbestos on the linings of the outdoor learning area as listed on the School Asbestos Management Plan. Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. All materials are currently undisturbed and in good condition. |
|
|
Removal and replacement of window and eaves on the northern side of Building A |
Removal of eaves containing bonded asbestos as listed on the School Asbestos Management Plan. Material undisturbed and in good condition. |
|
|
Floor covering replacement in Building B |
Removal of vinyl tiles known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Remediation of soil under a concrete slab near the oval. |
Encapsulation of soil, which contains bonded asbestos containing material as listed on the School Asbestos Management Plan. |
|
|
Resurfacing the quad area |
Removal of assumed in-ground asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
School holiday work school list T-Z
|
School |
What work we’re doing and where |
More detail about the work involving hazardous materials |
|---|---|---|
|
Window replacement in Building B art room. |
Removal of window putty assumed to contain bonded asbestos, recently identified but not listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Improvements to outside areas surrounding buildings A and B including repair and renewal of concrete surfaces. |
No hazardous material involved. |
|
|
Installation of new carpet and vinyl flooring in Building A. |
Removal of vinyl tiles, under existing carpet, known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Planned remediation of grassed area between the administration block, Building K and Building J. |
Encapsulation of soil, which contains bonded asbestos, as listed on the School Asbestos Management Plan by covering with a fabric lining and topping it with a clean soil. |
|
|
Installation of new carpet and vinyl flooring in the library and reading rooms of Building A. |
Removal of vinyl tiles, under existing carpet, known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Floor replacement in all rooms in the Administration block in Building E. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of the ceiling lining in the movement area and plant room on the ground floor of Building G. |
Removal of ceiling lining panels containing bonded asbestos as listed on the School Asbestos Management Plan. Materials are currently undisturbed and in good condition. |
|
|
Installation of a new roof on Building D. |
Remediation of the roof cavity from lead dust prior to replacing the roof. |
|
|
Refurbishment of the student toilets in Building F. |
Removal of external eaves known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Window replacement in Building B art room |
Removal of window putty assumed to contain bonded asbestos, recently identified but not listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Upgrade to floor coverings in one Building D classroom. |
Works involves planned removal of bonded asbestos floor tiles listed on the School Asbestos Management Plan. The tiles are in good condition and located under carpet. |
|
|
Repairs and upgrades to Building A to remediate mould-affected areas. |
Removal and replacement of building finishes affected by mould and work to prevent further mould-related issues. |
|
|
Installation of new carpets in 4 classrooms within Building A. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Roof replacement of the library building in Building L. |
Removal of bonded asbestos from the roof eaves as listed on the School Asbestos Management Plan. Material is currently undisturbed and in good condition. |
|
|
Upgrades to the covered walkway between buildings A and B. |
Removal of eave sheets known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is currently undisturbed and in good condition. |
|
|
Replacement of ceiling sheets in a movement area of Building C to gain access to the ceiling joists and bearers as part of an upgrade. Floor covering replacement in Building B. |
The ceiling sheeting contains bonded asbestos, as identified in the School Asbestos Management Plan, and will be replaced with fibre cement sheeting. Removal of existing vinyl tiles which contain bonded asbestos as listed on the School Asbestos Management Plan. Material is currently undisturbed and in good condition. |
|
|
Refurbishment to the toilets in Building M including new tiles, fixtures and partitions. |
Removal of cubicle partitions known to contain bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Floor replacement in the counsellor room in Building C, staffroom and deputy principal's office in Building D and kindergarten classrooms in Building F. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the movement area in Building D. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Toilet refurbishment in Building C |
Removal of known bonded asbestos in toilet partitions and ceiling linings as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Hall refurbishment. |
Removal of known bonded asbestos located in the wall and ceiling sheets of the hall as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Removal and replacement of walls, ceiling lining panels and window in the office next to the canteen in Building D. |
Removal of ceiling lining panels containing bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed. |
|
|
Replacement of carpet in various classrooms. |
Carpet will be replaced in some rooms listed on the School Asbestos Management Plan where old bonded asbestos tiles are present. The tiles are in good condition and located under carpet. |
|
|
Remediation and removal of asbestos in the ceiling cavity above the canteen and the girls toilets in Building B. |
Remediation and removal of friable asbestos in the ceiling cavity above the canteen and the girls toilets in Building B. The area is listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacing carpet in Building A classrooms. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacing carpet in the STEM room in Building C. |
Removal of vinyl tiles containing bonded asbestos under existing carpet as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Refurbishment of support unit class in Building B. |
Removal of fibro sheeting containing bonded asbestos behind a wall lining in Building B, recently identified but not listed on the School Asbestos Management Plan. |
|
|
Replacement of carpet in various classrooms. |
Carpet will be replaced in some rooms listed on the School Asbestos Management Plan where old bonded asbestos tiles are present. All work will be carried out under the supervision of an independent hygienist with temporary barriers, signage and continuous air monitoring in place. |
|
|
Replacement of floor coverings in the photocopy room in Building A, one classroom in Building E and 2 classrooms in Building I. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Removal and replacement of windows, eaves and external painting in buildings D and E. |
Removal of existing eaves which contain bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Floor covering replacement in movement area and stage 2 and 3 classrooms of Building B and the computer lab in Building I. |
Removal of existing vinyl flooring which contains bonded asbestosas listed on the School Asbestos Management Plan . Material currently undisturbed and in good condition. |
|
|
Installation of new windows on the southern side of Building L. |
Removal of window cladding containing bonded asbestos as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Upgrades and additions to the covered walkway between buildings F and G |
Removal of known in-ground asbestos from the area between buildings F and G as listed on the School Asbestos Management Plan. Material is undisturbed and in good condition. |
|
|
Replacement of floor coverings in movement area of the ground level of Building B. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |
|
|
Replacement of floor coverings in the movement area, 2 classrooms and clerical rooms on the ground floor and 3 classrooms on the first floor in the Administration building in Building A. |
Removal of existing vinyl flooring which contains bonded asbestos as listed on the School Asbestos Management Plan. Material currently undisturbed and in good condition. |