In the new building, internal walls and ceilings will be put up, the outside cladding will be finished, and the covered walkway will be paved.
In the upcoming school holidays, we will begin to upgrade the schools ICT equipment to provide faster, more reliable network access to support teaching and learning. These works will involve digging trenches and laying underground cables throughout the school site. We will also upgrade the fire hydrant booster.
Refurbishment works will begin In Block A, including refreshing the Principal’s office, constructing the new sick bay, refurbishing part of the reception area, creating a new staff room, installing new doors in the corridor and converting one of the staff toilets into an accessible toilet.
These works have been scheduled to take place in the school holidays to minimise any disruption.